* Factory acceptance tests (Level 1 commissioning): Testing of products prior to leaving their place of manufacture
* Field component verification (Level 2 commissioning): Inspection and verification of products upon receipt
* System construction verification (Level 3 commissioning): Field inspections and certifications that components are assembled and properly integrated into systems as required by plans and specifications
* Site acceptance testing (Level 4 commissioning): Activities that demonstrate that related components, equipment, and ancillaries that make up a defined system operate and function to rated, specified, and/or advertised performance criteria
* Integrated systems tests (Level 5 commissioning): Testing of redundant and backup components, systems, and groups of interrelated systems to demonstrate that they respond as predicted to expected and unexpected anomalies

Glossary Category: